Project Profile Case Study

When a 114-year-old culvert collapsed below Washington Street near downtown Waukegan, Illinois, the result was a 45-foot deep sinkhole that required emergency repairs. The situation deteriorated after a rainstorm. Immediate repairs were essential to avoid rupturing a sanitary line that could end up flowing into Lake Michigan.

Washington Street is a four-lane arterial street with sidewalks on each side. Inside the sinkhole, 45 feet below roadway grade, lay a 10-foot-diameter, stone pipe arch. Constructed in 1904, the 180-foot-long arch carries the Waukegan River underground. When the interior of the arch was inspected, it was discovered that a portion of the arch wall had collapsed, causing the sinkhole.

It was determined that a 10-foot-diameter reinforced concrete pipe would be the best repair from a combined hydraulic, constructability and availability perspective. Reinforced concrete pipe would provide the strength, resilience and dependability needed for the project. Plus, it was quickly available to the contractor, Campanailla & Sons, and could be delivered on short notice so the road could return to service as soon as possible.

Design and Installation
For this job, the concrete pipe used 10-foot diameter cages that were built in-house in a day. The manufacturer could provide a fast turnaround, which was necessary for this emergency repair. Production of the pipe started within 3 to 4 days of the order. It was considered a specialty design because the project involved 33 feet of cover on top of the 10-foot-diameter pipe. The pipe measured 7 feet, 6 inches long with a 12-inch wall. Stirrups were placed in the crown and invert to accommodate the shear forces from the 33 feet of cover. Reinforced concrete pipe is a structure that allows the designer to add additional strength, which is sometimes required.

The contractor followed ACPA recommendations for installing large pipes. A dead man restraint was placed in the initial installation to pull the pipe joint into place through mechanical force (pipe puller). The pipe puller remains in place, and each additional joint of pipe is winched home. When the pipe puller cable is not long enough, the pipe puller is reset further into the pipe. This type of installation leads to much straighter, uniform joints. Alternate methods of pushing the pipe into place with construction equipment are against ACPA recommendations, as it can damage the pipe and would typically lead to poor joints and alignment of the culvert.

Meeting the Challenges
In the span of two months, the 114-year-old arch was cut open and then replaced with the 10-foot diameter precast concrete pipe. The weather was always a factor since a rainstorm could delay a quick repair, and more damage could incur if the arch continued to deteriorate.

The replacement of the half-collapsed stone arch culvert required an open excavation. It was challenging to maintain stability of the steep slopes during rain. To add to this, an unrelated water-main failure at a nearby retirement home created some additional erosion to the slopes of the excavation.
One of the challenges of the project was maintaining an AT&T fiberoptic line that had to be structurally reinforced so it could be supported in place by two cranes (a 200-ton and 165-ton) during final excavation and installation of the concrete pipe.

During the installation, an invert of the new culvert was set 6 inches below the stream bed elevation to allow the bottom of the culvert to fill in with sediment, imitating a natural streambed. This method provides a better habitat for fish and other stream inhabitants.

Despite the severity of the culvert collapse, precast reinforced concrete pipe allowed for a quick, long-lasting structural repair.The community was able to quickly resume use of the road, and the Department of Public Works was relieved that the nearby sanitary line was not ruptured.

Location: Waukegan, IL
Date Completed: December 10, 2018
Project Owner: City of Waukegan, IL
Contractor: Campanailla & Sons
Precast Supplier: Oldcastle Infrastructure
Engineer: Ciorba Group Ltd

This is a demonstration of the comparative flammability of polypropylene pipe (PP), reinforced concrete pipe (RCP), and high density polyethylene pipe (HDPE). Dry hay is ignited in three 18 in. by 18 in. pipes and allowed to burn. This is an unedited test conducted on October 21, 2015.

Georgia – September 2022 – The Georgia Concrete Pipe Association (GCPA) is pleased to announce it has named Joe Chevrier to the position of State Engineer for Georgia. In his new role, Joe will work closely with the concrete pipe industry professionals from across the state to assist & support local municipalities, DOT engineers, and other […]

Irving, Texas – August 04, 2022 – The American Concrete Pipe Association (ACPA) is proud to announce its annual Concrete Pipe Week will be held August 14-20, 2022. Concrete Pipe Week recognizes the significance and affirms the contributions the reinforced concrete pipe and precast industry has to a community’s quality of life. This year’s Concrete […]

Irving, Texas – April 6, 2022 – The American Concrete Pipe Association (ACPA) is pleased to announce the association’s new Chairman of the Board is Kurt Johnson, Vice President of Pipe and Precast at Geneva Pipe and Precast, a Northwest Pipe Company. Johnson was confirmed as Chairman during the ACPA’s Annual Convention held March 27-29. […]

By Mel Marshall, Mel C. Marshall Industrial Consultants Reinforced concrete pipe is widely known for its long history, with evidence of the first concrete pipe sanitary sewer in America dating back to 1842 in Mohawk, N.Y. Since then, concrete wastewater pipelines have grown increasingly more complex in their design, manufacture, installation, and inspection. As the […]

Irving, Texas – February 24, 2022 – The American Concrete Pipe Association (ACPA) is excited to announce the registration for an encore presentation of Pipe School 2022 is now open. Due to the success of the hybrid in-person and virtual Pipe School 2022 in Frisco, Texas, the ACPA decided to open the event to a […]

ACPA President, Steven Hawkins, AIA

Irving, Texas – January 6, 2022 – The American Concrete Pipe Association (ACPA) is excited to announce that Steven Hawkins, AIA, CSI, has been named its new president. The appointment came after an extensive nationwide search and has been approved by the ACPA Board of Directors. “Steve is an excellent choice to continue the strong […]

By Margarita Takou, Ph.D., P.E., ACPA Technical Resource Manager At the ACPA, we talk a lot about the benefits of precast reinforced concrete pipe (RCP), but did you know the association’s membership also produces precast reinforced concrete box culverts? Like RCP, box culverts offer the benefits of precast concrete construction such as superior durability strength, […]

ACPA Press Release - Pipe School 2022

Registration Open for Pipe School 2022 Back in-person and with a special streaming option for transportation agency personnel Irving, Texas – Irving, Texas – November 17, 2021 – The American Concrete Pipe Association (ACPA) is excited to announce the opening of registration for Pipe School 2022. Back in-person for 2022, Pipe School will be held […]

Infrastructure statement from Branimir Kovac

Irving, Texas – November 6, 2021 – Late on November 5th, the U.S. House of Representatives voted to pass landmark infrastructure legislation, clearing the measure for the President’s signature. The American Concrete Pipe Association (ACPA) applauds the Congress for taking this action.  The legislation – called the “Infrastructure Investment and Jobs Act” or IIJA – will […]