Project Profile Case Study

As the 20th anniversary of a significant canal breach in Utah passed, the canal company’s investment in repairs and replacement are a triumph for the water users and the engineering community. Precast concrete products have been integral to the improvements.

On July 11, 1999, the Davis and Weber Canal breached. Nearby Riverdale City homes faced the brunt of the flood, as muddy water and silt forced hundreds of residents to evacuate. Fortunately, no lives were lost, yet the deluge damaged more than 70 houses and caused the need for canal repairs that would ultimately cost upwards of $10 million.

Now, 20 years later, critical sections of the canal have been replaced through company funds, extensive state loans and federal grant funding. Due to its benefits including strength, durability and resiliency, reinforced precast concrete box culvert (RCB) was used in several locations as the canal has been replaced and enclosed.

Century of History

The original, earthen Davis and Weber Counties Canal dates to the mid 1880s when it was constructed to carry water to the early settlement farmlands in Weber and Davis Counties. Ranging in widths from 10 to 20 feet, the rough and uneven canal was reconstructed by 1911 and lined with concrete. Workers placed tightly rolled wool rope material in the concrete joints to allow for the concrete’s expansion and contraction. However, by 1915, the joints began to leak due to the wool’s deterioration. Over the years, the canal underwent numerous repairs until today, when more than half the canal system has been replaced with cast-in-place box culvert, precast box culvert, large concrete pipes or concrete trapezoidal liner with water stop. 

Post-Breach Repairs

The Davis and Weber Counties Canal Company (DWCCC) had J-U-B Engineers of Kaysville, Utah, which had worked for the canal company since the late 1980s, design the repairs through the breach. J-U-B also prepared and executed initially a long-term plan for the design and construction of improvements for the upper 9 miles of the 17.2-mile-long canal. Now there is a complete improvement plan for the entire canal system, updated by a Bureau of Reclamation System Optimization Review grant.

In addition to the breach, the improvements included replacing the most critical areas of the canal. The capital improvements solved several issues, including: leakage, vegetation growth, evaporation, algae growth, etc.  Leakage was estimated at nearly 30 percent in the upper section of the canal. Watertight joints have greatly reduced this leakage and saved roughly 30 percent, which means additional water for the end users.

To obtain funding, DWCCC was able to secure State of Utah, Board of Water Resources loans to make improvements and continues to pay off such indebtedness. The company was also successful in receiving ARRA federal grants and Bureau of Reclamation WaterSMART grant monies, which still require a minimum of 50 percent match. To date, more than $39 million of improvements have been completed on the overall canal system.

“Reinforced concrete box culvert was used in much of the canal, as it provided a structure that fit the profile of the canal and protected the canal against landslides. It also provided a closed conduit that provided better more secure water conveyance,” says Bryce Wilcox, J-U-B Engineers.

In several places, the canal was enclosed by going to reinforced concrete box culverts to avoid rock or debris slides, eliminate airborne debris entering the canal, and to improve safety. RCB was chosen for its strength, longevity and constructability.

Local precast concrete suppliers worked closely with J-U-B to assist with design, alignments and constructability. Careful coordination and strong relationships among members of the project team have facilitated a positive outcome.

“The Canal Company is pleased with all of the canal system improvements by maintaining a historical water conveyance system to the community as it transitions from agriculture to residential,” says Rick Smith, General Manager, DWCCC. “Water is necessary to maintain the quality of life.”

Project Team
Engineer of Record: J-U-B Engineers, Inc.
Contractors: Bowen Construction, Whitaker Construction, Reynolds Excavation, Flare Construction, Gerber Construction
Precast Supplier: Oldcastle Infrastructure, Geneva Pipe and Precast
Funding: State of Utah/Board of Water Resources, Bureau of Reclamation (WaterSMART)

This is a demonstration of the comparative flammability of polypropylene pipe (PP), reinforced concrete pipe (RCP), and high density polyethylene pipe (HDPE). Dry hay is ignited in three 18 in. by 18 in. pipes and allowed to burn. This is an unedited test conducted on October 21, 2015.

Georgia – September 2022 – The Georgia Concrete Pipe Association (GCPA) is pleased to announce it has named Joe Chevrier to the position of State Engineer for Georgia. In his new role, Joe will work closely with the concrete pipe industry professionals from across the state to assist & support local municipalities, DOT engineers, and other […]

Irving, Texas – August 04, 2022 – The American Concrete Pipe Association (ACPA) is proud to announce its annual Concrete Pipe Week will be held August 14-20, 2022. Concrete Pipe Week recognizes the significance and affirms the contributions the reinforced concrete pipe and precast industry has to a community’s quality of life. This year’s Concrete […]

Irving, Texas – April 6, 2022 – The American Concrete Pipe Association (ACPA) is pleased to announce the association’s new Chairman of the Board is Kurt Johnson, Vice President of Pipe and Precast at Geneva Pipe and Precast, a Northwest Pipe Company. Johnson was confirmed as Chairman during the ACPA’s Annual Convention held March 27-29. […]

By Mel Marshall, Mel C. Marshall Industrial Consultants Reinforced concrete pipe is widely known for its long history, with evidence of the first concrete pipe sanitary sewer in America dating back to 1842 in Mohawk, N.Y. Since then, concrete wastewater pipelines have grown increasingly more complex in their design, manufacture, installation, and inspection. As the […]

Irving, Texas – February 24, 2022 – The American Concrete Pipe Association (ACPA) is excited to announce the registration for an encore presentation of Pipe School 2022 is now open. Due to the success of the hybrid in-person and virtual Pipe School 2022 in Frisco, Texas, the ACPA decided to open the event to a […]

ACPA President, Steven Hawkins, AIA

Irving, Texas – January 6, 2022 – The American Concrete Pipe Association (ACPA) is excited to announce that Steven Hawkins, AIA, CSI, has been named its new president. The appointment came after an extensive nationwide search and has been approved by the ACPA Board of Directors. “Steve is an excellent choice to continue the strong […]

By Margarita Takou, Ph.D., P.E., ACPA Technical Resource Manager At the ACPA, we talk a lot about the benefits of precast reinforced concrete pipe (RCP), but did you know the association’s membership also produces precast reinforced concrete box culverts? Like RCP, box culverts offer the benefits of precast concrete construction such as superior durability strength, […]

ACPA Press Release - Pipe School 2022

Registration Open for Pipe School 2022 Back in-person and with a special streaming option for transportation agency personnel Irving, Texas – Irving, Texas – November 17, 2021 – The American Concrete Pipe Association (ACPA) is excited to announce the opening of registration for Pipe School 2022. Back in-person for 2022, Pipe School will be held […]

Infrastructure statement from Branimir Kovac

Irving, Texas – November 6, 2021 – Late on November 5th, the U.S. House of Representatives voted to pass landmark infrastructure legislation, clearing the measure for the President’s signature. The American Concrete Pipe Association (ACPA) applauds the Congress for taking this action.  The legislation – called the “Infrastructure Investment and Jobs Act” or IIJA – will […]